Ruland Road Substation Expansion

As part of our commitment to delivering safe, reliable energy, PSEG Long Island is continuously improving local infrastructure to ensure you have power whenever you need it – especially during severe weather. Over the next few months, you will see crews working in your neighborhood to strengthen the electric system. We recognize that multiple infrastructure projects are currently underway in your area. This specific project is part of our broader ongoing effort to modernize the grid and support our community’s growing demand for electricity. As local development continues, these upgrades will ensure our system remains resilient and prepared for both current and future needs. We are coordinating our efforts closely to minimize disruption to your neighborhood, and we appreciate your patience as we complete this vital work.

Project Specifics
PSEG Long Island will be replacing approximately 3,200 feet of underground cable, conduit and electric facilities. The project will utilize horizontal directional drilling to minimize the need to trench or otherwise disturb roadway or properties. Temporary drill pits will be installed in some areas, and limited trenching will be required to tie-in the new cable to existing equipment. These upgrades will ensure that you and your neighbors receive safe, reliable electric power for years to come. 

Project Timeline
Construction is expected to begin in October, with completion anticipated in December 2026. 

Project Route
Our crews will begin work at the LIPA substation on Ruland Road. From the substation entrance, crews will use horizontal directional drilling to install the infrastructure beneath Ruland Road and continue along the south side of the roadway, proceeding northeast toward Republic Road. Work will continue through the wooded right-of-way just beyond Republic Road. Crews will then proceed beneath Clubhouse Circle and Deshon Drive, with work concluding on the east side of Deshon Drive. Please see the map below.

Ruland Exit Feeder


Frequently Asked Questions

In addition to the work being performed at the substation described earlier, we will trim trees where necessary, and or remove vegetation following our utility bestpractice model and in coordination with appropriate government agencies.

  • Will there be any traffic interruptions?
    There will be traffic and parking disruptions along the project route and immediate area while work is being performed. To ensure traffic moves safely, PSEG Long Island will provide cones, flaggers and signage at the worksite, as needed. 
  • Will there be any power outages?
    PSEG Long Island does not anticipate any planned power outages related to this project. In the event that a brief planned outage is required, all affected customers will be notified in advance.
  • How can I get more information or leave feedback?
    If you have further questions or are unable to access the documents electronically and would like to request hard copies, please call PSEG Long Island Customer Service at 1-800-490-0025 between 8 AM and 8 PM. If you would like to leave feedback about this project, please take our survey at psegliny.com/inthecommunity/currentinitiatives/reliabilityprojects or email ExternalAffairsLI@psegliny.com 
     

 

 

 


POSTED DATE: 10/14/26