Hamlet of Hicksville (Town of Oyster Bay) 

Start date: Early April 2023
Posted date: March 24, 2023

The route will cover approximately 4.86 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
N. Newbridge Road between Mockingbird Lane and Flamingo Road
Newbridge Road between Flamingo Road and Albany Street
Rear property along Elmira Street between Newbridge Road and Blueberry Lane
Rear property along Blueberry Lane between Elmira Street and Genesee Street
Classic Drive between Genesee Street and Old Country Road
Rear property along Mockingbird Lane between N Newbridge Road and Orchid Road
Rear property along Pintall Lane and Kingfisher Road
Rear property along Falcon Lane and Blackbird Lane between Finch Lane and Flamingo Road
Rear property along Blacksmith Road E between Potter Lane and Saddler Lane
Rear property along Spindle Road between Friendly Road and Gulf Road
Rear property along Table Lane between Gulf Road and N Newbridge Road
Horn Lane between Blacksmith Road and Spindle Road
Division Street between Spindle Road and Alexander Avenue


Hicksville (Town of Oyster Bay) East Meadow and Salisbury (Town of Hempstead)

Start Date: January 2022
Posted Date: December 17, 2021

The route will cover approximately 1.31 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
West Old Country Road between Tec Street and Mead Avenue
Stewart Avenue between Choir Lane S and Levittown Parkway


Village of Cove Neck

Start Date: January 2022
Posted Date: December 21, 2021

The route will cover approximately 0.81 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Larrabee Avenue between W Main Street and Shore Avenue
Shore Avenue between West End Avenue and Maxwell Avenue
East Main Street between South Street and Pearl Street
White Street (turning into Elsie Avenue) between East Main Street and South Street
Cove Neck Road between Cove Road and east on Tiffany Road


Syosset

Start Date: April 2022
Posted Date: March 21, 2022

The route will cover approximately 1.29 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Jericho Turnpike between Underhill Boulevard and S Oyster Bay Road
Hasket Drive between Underhill Boulevard Cedar Place
Lafayette Drive between Jericho Boulevard and the end of Lafayette Drive
Humphrey Drive between Jericho Turnpike and Edward Avenue
Edwards Avenue between Humphrey Drive and Jackson Avenue
Jackson Avenue between S Oyster Bay Road and Dorcas Avenue


Seaford, Massapequa and North Massapequa

Start Date: May 2022
Posted Date: April 21, 2022

The route will cover approximately 2.14 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Clark Avenue between Riverside Avenue and Franklin Avenue
Forest Avenue between Parkhill Avenue and Michigan Avenue
Seaford Avenue between Chicago Avenue and New York Avenue
North of N Poplar Street between N Central Avenue and N Broadway
N Poplar Street between Park Avenue and N Broadway
N Central Avenue between N Poplar Street N Hickory Street
N Beech Street between Park Avenue and N Bay Avenue
N Pine between Park Avenue and N Bay Avenue
N Cedar between Park Avenue and N Bay Avenue
N Cedar Street between Park Avenue and N Bay Avenue
N Maple Street between Park Avenue and N Bay Avenue
N Walnut Street between Park Avenue and N Bay Avenue


Village of  Farmingdale and the Hamlets of South Farmingdale and East Farmingdale

Start Date: Early October 2022
Posted Date: September 22, 2022

The route will cover approximately 4.48 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Fulton Street between Main Street and E Carmans Road
Main Street between Fulton Street and Staples Street
Sunset Avenue between Main Street and Matthew Street
4th Avenue turning into Matthew Street between Woodward Parkway and Diana Drive
Crestwood Boulevard between Matthew Street and Milford Place
Rear property west of Diana Drive between Matthew Street and Eagle Lane
Rear property north of Eagle Lane between Carmans Road and west of Diane Drive 
Carmans Road between Main Street and Southern State Parkway
Fallwood Parkway between Merritts Road and Powell Street
Vandewater Street between Fallwood Parkway and Spielman Avenue
Spielman Avenue between Woodward Parkway and Vandewater Street
Woodward Parkway between Spielman Avenue and 4th Avenue


Hamlet of North Massapequa

Start Date: Late October 2022
Posted Date: September 28, 2022

The route will cover approximately .90 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
N Albany Avenue between just west of N Bay Avenue and N Broadway
N Broadway between N Linden and N Utica Avenue
N Linden between N Broadway and east of N Pine Drive
N Summit Drive between N Linden Street and N Elm Street


Hamlet of East Massapequa

Start Date: Early January 2023 
Posted Date: December 23, 2022

The route will cover approximately 2.6 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
E Chestnut Street between Dover Street and Clocks Boulevard
Clocks Boulevard between E Chestnut Street and Louden Avenue
E Cedar Street between Clicks Boulevard and Kenwood Avenue
Louden Avenue between Clocks Boulevard and East of Country Line Road
Country Line Road between E Pine Street and Ritter Avenue
Ritter Avenue between Broadway and West of Country Line Road
Broadway between Ritter Avenue and Brefni Street
Marilyn Avenue between Country Line Road and Broadway
Washington Avenue between Country Line Road and Broadway


City of Glen Cove, Hamlet of Glen Head and Village of Sea Cliff 

Start Date: Mid January 2023 
Posted Date: January 6, 2023

The route will cover approximately 1.57 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Roslyn Drive between Maiden Lane and west of Chestnut Place
Along a private road just south of Sea Cliff Avenue and east of the railroad
Sea Cliff Avenue between Glen Cove Avenue and Pratt Boulevard
Glen Cove Avenue between Sea Cliff Avenue and Shore Road
Altamont Avenue between Berkeley Place and Glen Cove Avenue


Town of Oyster Bay

Start Date: May 2021
Posted Date: April 28, 2021

The route will cover approximately 3.59 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
South Street between Elsie Avenue and Berry Hill Road
Orchard Street between Lexington Avenue and South Street
Burtis Avenue between South Street and Kellogg Street
Kellogg Street between Burtis Avenue and Berry Hill Road
Berry Hill Road between Park Avenue and Ivy Street
Anstice Street just north of intersection with Berry Hill Road
Singworth Street between Berry Hill Road and Oak Hill Drive
Rear property on north side of Oak Hill Drive, Park Place, Highwood Road and Schoolhouse Place between Singworth Street and just east of Huckleberry Lane
Rear property on east and south side of Huckleberry Lane
Rear property on east and south side of Highwood Road between Huckleberry Lane and Sugar Toms Lane
Sugar Toms Lane between Pine Hollow Road and just east of Ridge Rock Lane


Village of Brookville

Start Date: June 2021
Posted Date: May 18, 2021

The route will cover approximately 4.04 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Wheatley Road between Rolling Drive and Woodacres Road
Cedar Swamp Road (Route 107) between Meadowood Lane and Old Cedar Swamp Road
Fruitledge Road between Cedar Swamp Road (Route 107) and just north of Glenby Lane
Route 106 just north of intersection with Old Jericho Turnpike
Old Jericho Turnpike between intersection with Old Cedar Swamp Road and Karol Place


Village of Lattingtown

Start Date: September 2021
Posted Date: September 7, 2021

The route will cover approximately 0.17 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Lattingtown Road from west of Old Tappan Road to Parish Road
Old Tappan Road from just west of Overlook Road to Lattingtown Road
Feeks Lane from Coot Road to East of Coot Road


Locust Valley

Start Date: September 2021
Posted Date: September 7, 2021

The route will cover approximately 0.52 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
The Intersection of 13th Street and Cross Street
Cross Street between Lattingtown Road and Second Street
10th Street between Lattingtown Road and just south of Cross Street
Birch Hill Road between Davis Street and Cherry Street
Bayville Road between just north of Buckram Road to Long Island Rail Road Right of Way
Long Island Rail Road Right of Way (rear property along Buckram Road) between Bayville Road and Matinecock Court


Villages of Sea Cliff and Roslyn Harbor and the Hamlets of Glen Head and Glenwood Landing

Start Date: November 2021
Posted Date: November 8, 2021

The route will cover approximately 1.19 miles along an electric main line circuit.  PSEG Long Island crews will be working on the following streets:
12th Avenue between Roslyn Avenue and West of Central Avenue
Glenlawn Avenue between Brown Street and Littleworth Lane
Glen Cove Avenue between Plymouth Drive N and Todd Drive N
Glen Head Road between Brookwood Street and LIRR Right Of Way
Glen Cove Avenue between Glen Head Road and Smith Street
Glen Head Road and Oaklawn Avenue
Glen Head Road and Maple Place


Hicksville

Start Date: September 2021
Posted Date: September 7, 2021

The route will cover approximately 0.45 miles along an electric main line circuit., PSEG Long Island crews will be working on the following streets:
Jerusalem Avenue between 2nd Street and 7th Street
Jerusalem Avenue between Winding Road and South Dean Street


Village of Matinecock and City of Glen Cove

Start date: June 2020 
Posted date: June 8, 2020

The route will cover approximately 4.7 miles along an electric main line circuit . PSEG Long Island crews will be working on the following streets: 
Oyster Bay Road between Bayville Road and High Ridge Road 
Duck Pond Road between just west of Piping Rock Road to Oyster Bay Road 
Piping Rock Road between Underhill Road and Chicken Valley Road 
Long Island Rail Road right-of-way near Oyster Bay Road and Bayville Road


Plainedge

Start Date: April 2020 
Posted Date: April 2, 2020

The route will cover approximately 1.43 miles along an electric main line circuit.  PSEG Long Island crews will be working on the following streets: 
Hicksville Road between William Road and Ontario Avenue 
Jerusalem Avenue from just west of Hicksville Road to Flower Road