PSEG Long Island is committed to strengthening the electric infrastructure and improving reliability and will be continuing to storm harden the system. Power On will focus on mainline circuits, the backbone of PSEG Long Island’s distribution system. The mainlines feed the many branch lines that power the homes and businesses in your community.

For a list of completed projects, visit the Town of Huntington Completed Projects page.

 

West Hills and the Village of Huntington 

Start date: May 2020
Posted date: May 5, 2020

The route will cover approximately 4.38 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
11th Avenue between Craven Street and William Street
W 19th Street between 11th Avenue and W Hills Road
W 22nd Street between Joel Court and Patton Place
MacArthur Avenue between W 22nd Street and W Jericho Turnpike (Route 25)
Brooks Avenue between W 22nd Street and W Jericho Turnpike (Route 25)
W Jericho Turnpike (Route 25) between Brooks Avenue and Promenade Drive
Round Swamp Road between W Jericho Turnpike (Route 25) and Northern State Parkway


Northport

Start date: July 2020
Posted date: June 25, 2020

The route will cover approximately 1 mile along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
Elwood Road between north of Laurel Wood Road/Bellrose Avenue and 10th Avenue
Elwood Road between north of Fort Salonga Road and Belknap Drive
Fort Salonga Road between just west of Elwood Road and Jefferson Avenue
Scudder Avenue between Washington Place and Reservoir Avenue
Ocean Street between north of Nautilus Avenue to south of Steers Avenue 


Village of Lloyd Harbor

Start date: September 2020
Posted date: September 2, 2020 

The route will cover approximately 2.24 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets: 
School Lane between West Neck Road and where School Lane curves north
Harbor Hill Drive between West Neck Road and end of road rear property (Private Road)
Lloyd Harbor Road at the intersection of Fiddlers Green Drive 


Centerport and Greenlawn

Start date: September 2020
Posted date: September 16, 2020

The route will cover approximately 1.56 miles along an electric main line circuit. PSEG Long Island crews will be working on the following streets:
East Main Street (25A) between just east of Beaupre Court and Washington Drive
East Main Street (25A) between Cherry Lane and Lone Oak Drive
Greenlawn Road between just west of Cherry Lane and Dunlop Road
Greenlawn Road between just west of intersection with Dunlop Road and about 550 feet east of intersection with Dunlop Road
Lake Road between just north of Elks Court to north of Country View Lane


Town of Huntington

Start date: February 2021
Posted date: February 5, 2021

The route will cover approximately 2.04 miles along an electric main line circuit PSEG Long Island crews will be working on the following streets:
Park Avenue between Tasman Lane and just north of Woodhollow Lane
E Main Street (NY 25A) between Park Avenue and Washington Drive
Woodruff Court
Loma Place between E Main Street (NY 25A) and Greenlawn Road
North side, rear property of Huntington Bay Road between E Main Street (NY 25A) and Flower Hill Road