Transmission Owner Temporary Limitation

 

 

Date Time Post
 2/28/2024    12:14:26 PM Implementation table for East End Generation Start Procedure
Row 2, which assumes East Hampton DVAR available, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice.
 2/27/2024  20:34:57 PM  Implementation table for East End Generation Start Procedure
Row 12, which assumes East Hampton DVAR Out of Service, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice.
1/24/2024  17:12:00 PM Far Rockaway Generation
Far Rockaway generation may be needed due to transmission related work
Estimated start Time of 01/24/2024 18:00:00 and estimated end time of 01/30/2024 23:59:00
1/5/2024  00:58:12 AM Implementation table for East End Generation Start Procedure
Row 2, which assumes East Hampton DVAR available, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice.
  1/3/2024  2:17:17 PM  Implementation table for East End Generation Start Procedure
Row 10, which assumes East Hampton DVAR available, Canal DRSS DVAR 0% and Canal DRSS Caps Out of Service is now in effect. Estimated start Time of 01/04/2024 00:00:00 and estimated end Time of 01/04/2024 21:00:00 
 12/08/2023 2:15:00 PM Grumman Exit Limit

The combined exit limit of Calpine Bethpage 1,2,3 and 4 is no longer in effect as of 12/08/2023  14:15:00

12/04/23  11:34:00 AM 

Grumman Exit Limit

The combined exit limit of Calpine Bethpage 1,2,3 and 4 is 94 MWs due to a temporary transmission limitation.

  11/30/2023   6:47:13 PM Implementation table for East End Generation Start Procedure
Row 2, which assumes East Hampton DVAR available, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice. 

11/26/2023

10:00:00 AM

Implementation table for East End Generation Start Procedure
Row 5, which assumes East Hampton DVAR available, Canal DRSS DVAR 0% and Canal DRSS Caps Out of Service is now in effect. Estimated start Time of 11/26/2023 10:00:00 and estimated end time of 12/31/2023 23:59:00

  11/8/2023  9:21:21 AM  Implementation table for East End Generation Start Procedure
Row 2, which assumes East Hampton DVAR available, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice.
 8/21/2023   21:42:50 PM  Grumman Exit Limit

The combined exit limit of Calpine Bethpage 1,2,3 and 4 is no longer in effect as of  8/21/2023  19:59:16 PM. 

 08/19/2023 15:03:25 PM

 Grumman Exit Limit

The combined exit limit of Calpine Bethpage 1,2,3 and 4 is 72 MWs due to a temporary transmission limitation.

06/21/2023   18:24:57 PM  Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 06/21/2023 18:24:57 and estimated end time of 12/31/2023 23:59:00
06/16/2023  20:23:23 PM   Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice. Estimated start Time of 06162/2023 20:23:23 and estimated end time of 12/31/2023 23:59:00
 06/14/2023 23:51:58 PM Implementation Tables for G.3
Table 1 which assumes BOTH West Bus DRSS and Wildwood DRSS Out of Service is effective until further notice
Estimated start Time of 06/14/2023 23:51:58 and estimated end time of 12/31/2023 23:59:00
06/14/2023   00:27:00 AM

Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.

Estimated start Time of 06/14/2023 00:27:00 and estimated end time of 12/31/2023 23:59:00

06/09/2023  12:52:44 PM   Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 06/09/2023 12:52:44 and estimated end time of 12/31/2023 23:59:00
06/02/2023   12:44:53 PM  Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice. Estimated start Time of 06/02/2023 12:44:53 and estimated end time of 12/31/2023 23:59:00
05/23/2023 10:06:00 AM  Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 05/23/2023 10:06:00 and estimated end time of 12/31/2023 23:59:00
05/23/2023

07:13:41 AM

 Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice. Estimated start Time of 05/23/2023 07:13:41 and estimated end time of 12/31/2023 23:59:00

05/11/2023

 11:58:00 AM  Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 05/11/2023 11:58:00 and estimated end time of 12/31/2023 23:59:00
  05/08/2023

 

  12:20:14 AM
Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice. Estimated start Time of 05/08/2023 00:18:00 and estimated end time of 12/31/2023 23:59:00 
 05/05/2023 17:45:25 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 05/05/2023 17:45:25 and estimated end time of 12/31/2023 23:59:00
 05/01/2023 05:31:25 PM  Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice. Estimated start Time of 05/01/2023 05:31:25 and estimated end time of 05/05/2023 17:45:25
04/27/2023 19:27:00 PM

Northport Exit Limitation
The combined output limitation for Northport 3 and 4 has been lifted. Estimated start Time of 4/27/2023 19:27:00 and estimated end time of 12/31/2023 23:59:00

03/24/2023 20:32:10 PM
Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately. Estimated start Time of 03/24/2023 20:32:10 and estimated end time of 12/31/2023 23:59:00
03/24/2023 17:38:10 PM

Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice. Estimated start Time of 03/24/2023 17:38:10 and estimated end time of 12/31/2023 23:59:00

 02/13/2023  04:36:00 PM Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 480MWN. Estimated start Time of 12/05/2022 09:00:00 and estimated end time of 05/15/2023 23:59:00
 02/02/2023  02:44:00 PM  **This is a test**
 01/06/2023  10:58:00 AM  Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 480MWN. Estimated start Time of 12/05/2022 09:00:00 and estimated end time of 02/15/2023 23:59:00
 12/19/2022 09:21:00 AM Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 480MWN. Estimated start Time of 12/05/2022 09:00:00 and estimated end time of 01/15/2023 23:59:00
 12/05/2022 09:00:00 PM Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 480MWN. Estimated start Time of 12/05/2022 09:00:00 and estimated end time of 12/31/2022 23:59:00
 11/21/2022  03:33:00 PM  Northport Exit Limitation
The combined output of Northport 3 and 4 is no longer limited at this time. Estimated start Time of 07/18/2022 10:45:00 and estimated end time of 11/21/2022 15:33:00
 09/02/2022 09:15:00 AM Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 470MWN between 1000 and 2200 hours and 550MWN between 2200 and 1000 hours. Estimated start Time of 07/18/2022 10:45:00 and estimated end time of 12/31/2022 23:59:00
 08/01/2022 12:17:00 PM Implementation table for East End Generation Start Procedure
Row 1, which assumes East Hampton DVAR available, Canal DRSS DVAR 100% and Canal DRSS Caps Available is now in effect until further notice.  
 07/22/2022 13:45:00 Implementation table for East End Generation Start Procedure
Row 2, which assumes East Hampton DVAR available, Canal DRSS DVAR 75% and Canal DRSS Caps Available is now in effect until further notice.  
 07/19/2022 20:37:00

Neptune Limitation
The repairs on have been completed. Neptune is available for full capacity.

 07/19/2022 08:10:00 AM Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 470MWN between 1000 and 2200 hours and 550MWN between 2200 and 1000 hours. Estimated start Time of 07/18/2022 10:45:00 and estimated end time of 09/16/2022 23:59:00
 07/18/2022 10:45:00 AM

Northport Exit Limitation
The combined output of Northport 3 and 4 is limited to approximately 470MWN between 1000 and 2200 hours and 550MWN between 2200 and 1000 hours. Estimated start Time of 07/18/2022 10:45:00 and estimated end time of 08/01/2022 23:59:00

 07/15/2022 15:25:22  Implementation table for East End and South Fork Operating Guideline

CANAL DRSS IN SERVICE – FULL SYSTEM

Estimated start Time of 07/15/2022 15:25:00 and in effect until further notice

 07/15/2022 10:31:00 AM Implementation table for East End and South Fork Operating Guideline

CANAL DRSS IN SERVICE – DVAR ONLY - E HAMP D-VAR I/S

Estimated start Time of 07/15/2022 10:31:00 and estimated end time of 07/15/2022 15:00:00

 06/21/2022  12:45:00 PM The combined output of Northport 3 and 4 is limited to approximately 465MWN. Estimated start Time of 06/10/2022 00:01:00 and estimated end time of 06/24/2022 23:59:00
 06/11/2022  4:25:00 PM The combined output of Northport 3 and 4 is limited to approximately 465MWN. Estimated start Time of 06/10/2022 00:01:00 and estimated end time of 06/21/2022 23:59:00
 05/13/2022  17:26:00 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 05/13/2022 17:26:00 and estimated end time of 12/31/2022 23:59:00
 05/08/2022  11:50:00 PM  Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately.
Estimated start Time of 05/8/2022 23:50:00 and estimated end time of 12/31/2022 23:59:00
 05/07/2022  06:50:00 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 05/07/2022 18:50:00 and estimated end time of 12/31/2022 23:59:00
 05/06/2022  3:15:00 PM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately.
Estimated start Time of 05/6/2022 15:15:00 and estimated end time of 12/31/2022 23:59:00
 05/02/2022  07:43:07 AM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 05/02/2022 07:43:07 and estimated end time of 05/06/2022 23:59:00
 04/23/2022  3:16:34 PM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately.
Estimated start Time of 04/23/2022 15:16:34 and estimated end time of 12/31/2022 23:59:00
03/09/2022  18:50:00 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 03/09/2022 18:50:00 and estimated end time of 12/31/2022 23:59:00

03/09/2022

05:43:33 AM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 03/09/2022 05:43:33 and estimated end time of 12/31/2022 23:59:00
03/08/2022 01:20:57 PM  **TEST This is the Header Text**
** TEST This is the Body Text **
Estimated start Time of 03/08/2022 13:20:00 and estimated end time of 03/08/2022 13:30:00
12/28/2021 06:13:38 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 12/28/2021 18:12:00 and estimated end time of 12/31/2022 23:59:00
12/28/2021 12:30:47 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 12/28/2021 00:30:00 and estimated end time of 12/31/2021 23:59:00
11/22/2021 02:42:15 PM Far Rockaway Generation
Due to system conditions Far Rockaway generation may be required. Estimated Start Time of 11/22/2021 14:30:00 and Estimated End Time of 11/24/2021 23:59:59
Estimated start Time of 11/22/2021 14:30:00 and estimated end time of 11/24/2021 23:59:00
11/15/2021 10:16:57 AM East of Riverhead Generation Required
Additional on island generation required east of Riverhead due to line outages and contingencies.
Estimated start Time of 11/15/2021 10:00:00 and estimated end time of 11/15/2021 23:59:00
10/16/2021 03:23:14 AM East of Holbrook Generation Required
Modification to end time of additional on island generation required east of Holbrook due to system conditions.
Estimated start Time of 10/16/2021 00:01:00 and estimated end time of 10/16/2021 04:00:00
10/15/2021 11:05:33 PM East of Holbrook Generation Required
Additional on island generation required east of Holbrook due to system conditions.
Estimated start Time of 10/16/2021 00:01:00 and estimated end time of 10/16/2021 11:00:00
09/24/2021 11:05:01 PM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 09/24/2021 23:00:00 and estimated end time of 12/31/2021 23:59:00
09/20/2021 07:46:41 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 09/20/2021 18:49:00 and estimated end time of 12/31/2021 23:59:00
09/19/2021 12:08:58 PM Northport Oil Operation
Due to system conditions, one (1) Northport Unit will be required on 75% oil while Y-50 is out of service.
Estimated start Time of 09/20/2021 00:00:00 and estimated end time of 09/20/2021 23:59:00
09/19/2021 10:11:20 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 09/19/2021 10:02:00 and estimated end time of 12/31/2021 23:59:00
09/17/2021 01:56:17 PM Northport Oil Operation
For system reliability at loads above 3500MW at least (1) Northport unit must be operated on Oil fuel. End date for this post has been updated.
Estimated start Time of 08/07/2021 16:00:00 and estimated end time of 09/19/2021 23:59:00
09/17/2021 08:56:01 AM Northport Oil Operation
Due to system conditions, (2) Northport units will be required on 75% Oil until further notice, to ensure system reliability. The post is updated to reflect the new end time.
Estimated start Time of 08/09/2021 15:00:00 and estimated end time of 09/19/2021 23:59:00
08/25/2021 11:24:17 AM Northport Oil Operation
Due to system conditions, a 3rd Northport unit will be required on 75% Oil to ensure system reliability.
Estimated start Time of 08/25/2021 08:00:00 and estimated end time of 08/27/2021 23:59:00
08/24/2021 08:13:01 AM Northport Oil Operation
Due to system conditions, a 3rd Northport unit will be required on 75% Oil to ensure system reliability.
Estimated start Time of 08/25/2021 08:00:00 and estimated end time of 08/26/2021 23:59:00
08/11/2021 11:46:39 AM Northport Oil Operation
Due to system conditions, a 3rd Northport unit will be required on 75% Oil to ensure system reliability.
Estimated start Time of 08/12/2021 07:00:00 and estimated end time of 08/13/2021 23:59:00
08/11/2021 11:28:02 AM Y-49 Estimated Return Time
The estimated return time for Y-49 is updated to be 10/15/2021 2359 hours.
Estimated start Time of 08/11/2021 00:00:00 and estimated end time of 08/11/2021 23:59:00
08/09/2021 02:58:22 PM Northport Oil Operation
Due to system conditions, (2) Northport units will be required on 75% Oil until further notice, to ensure system reliability.
Estimated start Time of 08/09/2021 15:00:00 and estimated end time of 12/31/2021 23:59:00
08/07/2021 04:13:19 PM Northport Oil Operation
For system reliability at loads above 3500MW at least (1) Northport unit must be operated on Oil fuel
Estimated start Time of 08/07/2021 16:00:00 and estimated end time of 12/31/2021 23:59:00
07/17/2021 06:48:25 PM On Island Generation Required
Additional Northport and Port Jeff generation required due to transmission system conditions.
Estimated start Time of 07/18/2021 00:01:00 and estimated end time of 07/18/2021 23:59:00
04/26/2021 10:41:56 PM Implementation Tables for G.3
Table 4, which assumes BOTH West Bus DRSS and Wildwood DRSS in service, is effective immediately.
Estimated start Time of 04/26/2021 22:30:00 and estimated end time of 12/31/2021 23:59:00
04/21/2021 09:08:16 AM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 04/21/2021 09:00:00 and estimated end time of 12/31/2021 23:59:00
04/21/2021 12:43:07 AM Implementation Tables for G.3
Table 1 which assumes BOTH West Bus DRSS and Wildwood DRSS Out of Service is effective until further notice
Estimated start Time of 04/21/2021 00:40:00 and estimated end time of 12/31/2021 23:59:00
04/12/2021 07:58:37 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 04/12/2021 07:45:00 and estimated end time of 12/31/2021 23:59:00
04/08/2021 05:12:37 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 04/08/2021 17:10:00 and estimated end time of 12/31/2021 23:59:00
04/04/2021 04:07:11 PM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 04/04/2021 16:00:00 and estimated end time of 12/31/2021 23:59:00
01/15/2021 03:50:52 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 01/15/2021 15:42:00 and estimated end time of 12/31/2021 23:59:00
01/14/2021 09:54:26 AM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 01/14/2021 09:43:00 and estimated end time of 12/31/2021 23:59:00
12/21/2020 03:42:17 AM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 12/21/2020 03:41:00 and estimated end time of 12/31/2020 23:59:00
12/19/2020 04:42:32 PM SRE Northport Generation for Local Security
SRE Northport 4 Generation for Local Security
Estimated start Time of 12/20/2020 11:00:00 and estimated end time of 12/20/2020 23:59:00
12/19/2020 12:32:47 AM Implementation Tables for G.3.
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 12/19/2020 00:15:00 and estimated end time of 12/21/2020 23:59:00
10/27/2020 05:52:36 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 10/27/2020 17:45:00 and estimated end time of 12/31/2020 23:59:00
10/25/2020 05:00:18 PM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 10/25/2020 17:00:00 and estimated end time of 10/31/2020 15:00:00
09/03/2020 04:40:39 PM Neptune Limitation
Neptune Intertie will be limited to 375 MW max for the duration of the posted hours due to system conditions.
Estimated start Time of 09/02/2020 18:30:00 and estimated end time of 09/30/2020 23:59:00
09/02/2020 10:01:49 PM Neptune Limitation
Neptune Intertie will be limited to 375 MW max for the duration of the posted hours due to system conditions.
Estimated start Time of 09/02/2020 18:30:00 and estimated end time of 09/04/2020 23:59:00
06/16/2020 10:40:31 AM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 06/16/2020 10:39:00 and estimated end time of 12/31/2020 23:59:00
06/16/2020 08:41:48 AM Implementation Tables for G.3
Table 3, which assumes the West Bus DRSS out of service and Wildwood DRSS in service, is effective until further notice.
Estimated start Time of 06/16/2020 08:05:00 and estimated end time of 12/31/2020 23:59:00
06/07/2020 04:41:20 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 06/07/2020 17:00:00 and estimated end time of 12/31/2020 23:59:00
06/06/2020 06:06:25 PM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 06/06/2020 15:04:00 and estimated end time of 12/31/2020 23:59:00
04/15/2020 07:42:18 PM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work
Estimated start Time of 04/13/2020 14:00:00 and estimated end time of 04/16/2020 23:59:00
04/15/2020 03:18:35 AM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work
Estimated start Time of 04/13/2020 14:00:00 and estimated end time of 04/15/2020 23:59:00
04/14/2020 10:53:56 AM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work
Estimated start Time of 04/13/2020 14:00:00 and estimated end time of 04/14/2020 23:59:00
04/13/2020 10:02:12 PM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work
Estimated start Time of 04/13/2020 14:00:00 and estimated end time of 04/14/2020 11:00:00
03/25/2020 08:14:31 PM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work Estimated start Time of 03/26/2020 05:00:00 and estimated end time of 03/26/2020 22:00:00
Estimated start Time of 03/26/2020 05:00:00 and estimated end time of 03/26/2020 22:00:00
02/06/2020 05:50:11 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 02/06/2020 17:36:00 and estimated end time of 12/31/2020 23:59:00
02/05/2020 08:52:19 AM Far Rockaway Generation
Far Rockaway generation will be needed due to transmission related work
Estimated start Time of 02/05/2020 07:00:00 and estimated end time of 02/05/2020 19:00:00
01/24/2020 12:17:40 PM Neptune Limitation
Neptune Intertie will be limited to 375 MW max for the duration of the posted hours due to system constraints.
Estimated start Time of 01/27/2020 00:00:00 and estimated end time of 01/27/2020 23:59:00
01/09/2020 10:28:50 PM SRE Northport Generation for Local Security
Due to unscheduled maintenance on LIPA power system, Northport Steam unit #4 will remain online for local reliability.
Estimated start Time of 01/10/2020 09:00:00 and estimated end time of 01/10/2020 21:00:00
12/31/2019 04:25:39 PM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 01/01/2020 00:00:00 and estimated end time of 01/31/2020 23:59:00
12/22/2019 06:59:45 AM Far Rockaway Generation
Due to system conditions Far Rockaway generation may be required.
Estimated start Time of 12/22/2019 07:00:00 and estimated end time of 12/22/2019 15:00:00
12/19/2019 04:59:24 AM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 12/19/2019 02:49:00 and estimated end time of 12/31/2019 23:59:00
11/25/2019 09:27:31 AM Test
This is a test message.
Estimated start Time of 11/26/2019 09:30:00 and estimated end time of 11/27/2019 22:50:00
11/08/2019 09:05:11 PM Far Rock Generation
Far Rockaway GT#1 will be online for local reliability
Estimated start Time of 11/08/2019 17:31:00 and estimated end time of 11/09/2019 10:00:00
09/30/2019 12:48:43 PM East End Generation
Due to transmission work on the LIPA system, East end generation may be required for local security.
Estimated start Time of 09/30/2019 12:30:00 and estimated end time of 10/03/2019 15:00:00
08/31/2019 12:32:29 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 08/31/2019 12:30:00 and estimated end time of 12/31/2019 23:59:00
08/30/2019 05:39:02 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 08/30/2019 02:30:00 and estimated end time of 12/31/2019 23:59:00
07/30/2019 08:07:35 AM East End Generation
Due to current system conditions additional generation may be required between the hours listed.
Estimated start Time of 07/30/2019 08:00:00 and estimated end time of 07/30/2019 12:00:00
07/26/2019 07:31:38 AM East End Generation
Due to current system conditions additional generation may be required between the hours listed above.
Estimated start Time of 07/26/2019 07:30:00 and estimated end time of 07/26/2019 23:59:00
07/05/2019 10:25:19 AM DARU Barrett 2
Barrett 2 will be online all day on 7/8/19 due to work on the LIPA transmission system
Estimated start Time of 07/08/2019 00:00:00 and estimated end time of 07/08/2019 23:59:00
07/05/2019 10:24:14 AM DARU Barrett 1
Barrett 1 will be online all day on 7/8/19 due to work on the LIPA transmission system.
Estimated start Time of 07/08/2019 00:00:00 and estimated end time of 07/08/2019 23:59:00
06/24/2019 06:43:37 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 06/24/2019 18:37:00 and estimated end time of 12/31/2019 23:59:00
06/19/2019 06:09:31 AM Far Rockaway Generation
Due to system conditions Far Rockaway generation may be required.
Estimated start Time of 06/19/2019 05:00:00 and estimated end time of 06/19/2019 23:59:00
05/07/2019 06:09:28 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 05/07/2019 17:07:00 and estimated end time of 12/31/2019 23:59:00
05/07/2019 12:45:40 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 05/07/2019 00:40:00 and estimated end time of 05/08/2019 15:00:00
04/05/2019 09:55:31 AM Far Rockaway Generation
Due to system conditions Far Rockaway generation may be required.
Estimated start Time of 04/05/2019 10:00:00 and estimated end time of 04/05/2019 23:00:00
02/22/2019 11:28:43 AM DARU Port Jeff Steam Unit# 4
Port Jeff Steam Unit# 4 to remain online for local reliability reasons.
Estimated start Time of 02/25/2019 06:00:00 and estimated end time of 02/26/2019 23:59:00
02/22/2019 11:12:52 AM DARU Barrett Steam Unit# 1
Barrett Steam Unit# 1 will remain online for local reliability reasons.
Estimated start Time of 02/25/2019 00:00:00 and estimated end time of 02/25/2019 23:59:00
02/20/2019 11:14:44 AM DARU Port Jeff Steam Unit# 4
Port Jeff Steam Unit# 4 will remain online for local reliability reasons. Time extended again by one (1) day.
Estimated start Time of 02/19/2019 06:00:00 and estimated end time of 02/22/2019 23:59:00
02/19/2019 10:24:43 AM DARU Port Jeff Steam Unit# 4
Port Jeff Steam Unit# 4 will remain online for local reliability reasons. Time extended by one (1) day.
Estimated start Time of 02/19/2019 06:00:00 and estimated end time of 02/21/2019 23:59:00
02/15/2019 10:35:08 AM DARU Port Jeff Steam Unit# 4
Port Jeff Steam Unit# 4 will remain online for local reliability reasons.
Estimated start Time of 02/19/2019 06:00:00 and estimated end time of 02/20/2019 23:59:00
02/11/2019 10:41:38 AM DARU Port Jeff Steam Unit
Port Jeff Steam Unit# 4 will remain online for local reliability reasons.
Estimated start Time of 02/13/2019 00:00:00 and estimated end time of 02/15/2019 23:59:00
02/08/2019 10:22:24 AM DARU Port Jefferson 4
Port Jefferson 4 will be online to secure the LIPA transmission system during system work.
Estimated start Time of 02/11/2019 06:00:00 and estimated end time of 02/12/2019 23:59:00
01/29/2019 11:01:02 AM DARU Port Jefferson Steam Unit #4
Port Jefferson Steam Unit# 4 will be online for Local Security Requirement
Estimated start Time of 01/31/2019 00:00:00 and estimated end time of 02/01/2019 23:59:00
01/28/2019 05:01:17 PM Implementation Tables for G.3
Table 4 which assumes both West Bus and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 01/28/2019 16:00:00 and estimated end time of 12/31/2019 23:59:00
01/28/2019 04:55:07 PM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 01/28/2019 16:00:00 and estimated end time of 12/31/2019 23:59:00
01/28/2019 02:11:42 PM DARU Port Jefferson Steam Unit #4
Port Jefferson Steam Unit# 4 will be online for reliability forecast beyond next day due to cold weather.
Estimated start Time of 01/30/2019 06:00:00 and estimated end time of 01/30/2019 23:59:00
01/27/2019 06:18:32 PM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 01/27/2019 18:13:00 and estimated end time of 01/28/2019 15:00:00
01/22/2019 01:01:37 PM DARU Port Jeff Steam
Port Jefferson Steam Unit# 4 will be online for local security requirements.
Estimated start Time of 01/24/2019 00:00:00 and estimated end time of 01/25/2019 23:59:00
01/18/2019 12:05:22 PM Port Jefferson 4 DARU
PJ 4 will be online for local security requirements.
Estimated start Time of 01/20/2019 00:00:00 and estimated end time of 01/20/2019 23:59:00
01/17/2019 02:42:03 PM DARU Npt 1 & 2, E W Barrett 1 & 2
Northport 1 & 2 and Barrett 1 & 2 will stay online due to unit downtime requirements if they were to be de-committed.
Estimated start Time of 01/19/2019 00:00:00 and estimated end time of 01/20/2019 23:59:00
01/14/2019 11:09:01 AM DARU Barrett Steam Unit# 2
Barrett Steam Unit# 2 will be online for local reliability.
Estimated start Time of 01/16/2019 00:00:00 and estimated end time of 01/16/2019 23:59:00
01/09/2019 05:04:23 PM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice
Estimated start Time of 01/09/2019 17:00:00 and estimated end time of 12/31/2019 23:59:00
01/08/2019 11:12:02 PM Implementation Tables for G.3.
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 01/09/2019 00:00:00 and estimated end time of 01/09/2019 23:59:00
12/07/2018 11:10:17 AM DARU Barrett Steam Unit #2
Barrett Steam Unit #2 will be online for local reliability.
Estimated start Time of 12/10/2018 00:00:00 and estimated end time of 12/11/2018 23:59:00
12/07/2018 11:07:15 AM DARU Barrett Steam Unit #2
Barrett Steam Unit #2 will be online for reliability beyond forecast.
Estimated start Time of 12/09/2018 00:00:00 and estimated end time of 12/09/2018 23:59:00
12/04/2018 10:36:45 AM DARU Barrett Steam Unit #2
Barrett Steam Unit #2 will be online for local reliability.
Estimated start Time of 12/06/2018 00:00:00 and estimated end time of 12/06/2018 23:59:00
11/30/2018 02:52:50 PM Transmission Constraint
Due to scheduled maintenance extra generation may be required east of Holbrook
Estimated start Time of 11/30/2018 14:45:00 and estimated end time of 11/30/2018 18:00:00
11/30/2018 10:45:13 AM DARU Barrett Steam for Local Security
Barrett Steam Unit 2 will remain online for Local Security reasons.
Estimated start Time of 12/03/2018 00:00:00 and estimated end time of 12/04/2018 23:59:00
11/08/2018 12:02:48 PM DARU Northport Steam for ARR 28A
Northport Unit# 3 will remain online for NYSRC Rule no. ARR 28A.
Estimated start Time of 11/10/2018 00:00:00 and estimated end time of 11/12/2018 23:59:00
10/19/2018 02:39:58 PM DARU Npt 2 for NYSRC RR . ARR 28A
Northport 2 will be online to satisfy NYSRC Reliability Rule no. ARR 28A which requires 1 Northport unit to be online during light load conditions.
Estimated start Time of 10/21/2018 00:00:00 and estimated end time of 10/23/2018 23:59:00
10/08/2018 03:34:37 PM test
testing i123
Estimated start Time of 10/12/2018 00:02:00 and estimated end time of 10/31/2018 02:05:00
10/05/2018 01:22:05 PM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice
Estimated start Time of 10/05/2018 13:17:00 and estimated end time of 12/31/2018 23:59:00
10/04/2018 03:54:56 PM DARU Northport Steam Unit
Northport Unit# 2 will remain online for Local Security Requirements.
Estimated start Time of 10/06/2018 00:00:00 and estimated end time of 10/07/2018 23:59:00
10/04/2018 08:45:09 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 10/03/2018 09:15:00 and estimated end time of 10/05/2018 23:59:00
10/03/2018 10:55:29 AM DARU Port Jeff Steam Units
Port Jeff Steam Units will be online to support Transmission related work. On 10/05/18 Unit# 4 should be online starting at 0600 hrs. On 10/07/18 both units should remain online for Downtime Requirements.
Estimated start Time of 10/05/2018 00:00:00 and estimated end time of 10/10/2018 23:59:00
10/03/2018 05:16:07 AM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice
Estimated start Time of 10/03/2018 05:00:00 and estimated end time of 12/31/2018 23:59:00
10/02/2018 11:16:59 AM DARU Port Jeff Steam
Port Jeff Steam Unit# 3 to remain online for Unit Downtime Requirements.
Estimated start Time of 10/04/2018 00:00:00 and estimated end time of 10/04/2018 23:59:00
10/01/2018 06:08:33 AM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 10/01/2018 06:00:00 and estimated end time of 10/03/2018 23:59:00
09/27/2018 08:41:26 PM
Due to transmission limitations East of Pilgrim additional generation will be required.
Estimated start Time of 09/27/2018 20:40:00 and estimated end time of 09/27/2018 23:59:00
09/25/2018 10:50:50 AM DARU Port Jeff Steam
Port Jeff Steam Unit# 3 will be online to prevent a contingency overload while transmission system work is conducted
Estimated start Time of 09/27/2018 00:00:00 and estimated end time of 09/27/2018 23:59:00
09/20/2018 10:22:06 AM DARU Barrett Steam
Barrett Steam Unit# 1 must be online to prevent a contingency overload while transmission system work is conducted
Estimated start Time of 09/22/2018 00:00:00 and estimated end time of 09/22/2018 23:59:00
09/09/2018 12:53:54 AM
Far Rockaway GT#1 will be online for local reliability
Estimated start Time of 09/08/2018 12:00:00 and estimated end time of 09/09/2018 06:00:00
09/09/2018 12:53:01 AM
Far Rockaway GT#1 will be online for local reliability
Estimated start Time of 09/08/2018 12:00:00 and estimated end time of 09/09/2018 23:00:00
09/08/2018 12:55:42 PM
Far Rockaway GT#1 will be online for local reliability
Estimated start Time of 09/08/2018 12:00:00 and estimated end time of 09/08/2018 23:59:00
09/07/2018 07:41:30 AM
Due to transmission limitations East of Pilgrim additional generation will be required.
Estimated start Time of 09/07/2018 07:00:00 and estimated end time of 09/07/2018 23:59:00
09/04/2018 10:28:17 AM ARR 28C DARU
Northport Units# 1,2 & 4 and Port Jeff Unit# 4 will be online for ARR 28C.
Estimated start Time of 09/06/2018 00:00:00 and estimated end time of 09/06/2018 23:59:00
08/31/2018 12:03:00 PM DARU Steam Units for ARR 28C
Northport Units# 1,2 & 4 and Port Jeff Unit# 4 will remain online for ARR 28C. Northport Unit# 2 will come online at 06:00 hrs.
Estimated start Time of 09/04/2018 00:00:00 and estimated end time of 09/04/2018 23:59:00
08/31/2018 11:59:46 AM DARU Steam Units
Northport Units# 1 & 4 will remain online for Unit Downtime Requirements. Port Jeff Unit# 4 will remain online for ARR 28C on 9/2 and Unit Downtime Requirements on 9/3.
Estimated start Time of 09/02/2018 00:00:00 and estimated end time of 09/03/2018 23:59:00
08/29/2018 11:25:52 AM DARU Steam Unit for Downtime Requirements
Port Jeff Steam Unit# 4 will be online for Unit Downtime Requirements.
Estimated start Time of 08/31/2018 00:00:00 and estimated end time of 08/31/2018 23:59:00
08/28/2018 01:13:44 PM 'NYSRC Reliability Rule no. ARR 28C
Northport 2, 3, 4 and Port Jefferson 3 will be online for 'NYSRC Reliability Rule no. ARR 28C.
Estimated start Time of 08/30/2018 00:00:00 and estimated end time of 08/30/2018 23:59:00
08/27/2018 11:43:29 AM DARU Steam Units
DARU Barrett Units 1 & 2 to avoid decommitment due to DARU of separate units. DARU Northport Units 1, 2, 3 & 4 and Port Jeff Units 3 & 4 for ARR 28C.
Estimated start Time of 08/29/2018 00:00:00 and estimated end time of 08/29/2018 23:59:00
08/24/2018 01:54:02 PM Revision: DARU Unit for ARR 28C
Northport Steam Unit # 1 will be online for ARR 28C.
Estimated start Time of 08/28/2018 06:00:00 and estimated end time of 08/28/2018 23:59:00
08/24/2018 01:49:48 PM DARU Units for ARR 28C
Following Steam Units will be online for ARR 28C: Northport # 2 starting at 10:00 on 8/27/18 Northport # 3 starting at 06:00 on 8/27/18 Northport # 4 starting at 00:00 on 8/27/18 Port Jeff # 3 starting at 00:00 on 8/27/18
Estimated start Time of 08/27/2018 00:00:00 and estimated end time of 08/28/2018 23:59:00
08/24/2018 12:14:44 PM DARU Unit for ARR 28C
Northport Steam Unit # 1 will be online for ARR 28C
Estimated start Time of 08/28/2018 00:00:00 and estimated end time of 08/28/2018 23:59:00
08/24/2018 12:12:00 PM DARU Units for ARR 28C
Northport Steam Units # 2, 3 & 4 and Port Jeff Steam Unit # 3 will be online for ARR 28C
Estimated start Time of 08/27/2018 00:00:00 and estimated end time of 08/28/2018 23:59:00
08/24/2018 12:04:26 PM DARU Untis to Avoid Decommitment
Barrett Stem Units # 1 & 2 will be online to avoid decommitment due to DARU of separate unit
Estimated start Time of 08/27/2018 00:00:00 and estimated end time of 08/28/2018 23:59:00
08/24/2018 12:00:15 PM DARU Units for Downtime Requirements
Barrett Steam Units # 1 & 2, Northport Steam Unit # 4 and Port Jeff Stem Unit # 3 will be online for Unit Downtime Requirements.
Estimated start Time of 08/26/2018 00:00:00 and estimated end time of 08/26/2018 23:59:00
08/16/2018 11:52:49 AM DARU units for ARR 28C
Northport Steam Unit # 4 will be online for ARR 28C
Estimated start Time of 08/18/2018 00:00:00 and estimated end time of 08/18/2018 23:59:00
08/15/2018 11:22:12 AM DARU units for ARR 28C
Northport Steam Units # 1, 3 & 4 and Port Jeff Steam Unit # 4 will be online for ARR 28C
Estimated start Time of 08/17/2018 00:00:00 and estimated end time of 08/17/2018 23:59:00
08/14/2018 10:30:08 AM DARU units for ARR 28C
Northport Steam Units #2, 3 & 4 and Port Jeff Steam Unit #3 & 4 will be online for ARR 28C.
Estimated start Time of 08/16/2018 00:00:00 and estimated end time of 08/16/2018 23:59:00
08/13/2018 12:58:15 PM East End Generation
All east end generation will need to run due to post contingency STE violations on the east end with Total south fork load greater than 140 MW
Estimated start Time of 08/11/2018 16:00:00 and estimated end time of 08/16/2018 23:59:00
08/13/2018 10:28:14 AM Npt & PJ DARU
Northport Steam Units #2, 3 & 4 and Port Jeff Steam Unit #4 will be online for ARR 28C
Estimated start Time of 08/15/2018 00:00:00 and estimated end time of 08/15/2018 23:59:00
08/11/2018 04:49:58 PM East End Generation
All east end generation will need to run due to post contingency STE violations on the east end with Total south fork load greater than 140 MW
Estimated start Time of 08/11/2018 16:00:00 and estimated end time of 08/14/2018 23:59:00
08/10/2018 01:20:01 PM DARU units for ARR 28C
Northport Steam Units # 3 & 4 will be online for ARR 28C
Estimated start Time of 08/13/2018 00:00:00 and estimated end time of 08/14/2018 23:59:00
08/10/2018 01:17:12 PM DARU Units for Downtime Requirements
Northport Steam Units # 3 & 4 will be online for Unit Downtime Requirements.
Estimated start Time of 08/12/2018 00:00:00 and estimated end time of 08/12/2018 23:59:00
08/08/2018 11:24:07 AM DARU units for ARR 28C
Northport Steam Units #1, 3 & 4 and Port Jeff Steam Unit #4 will be online for ARR 28C
Estimated start Time of 08/10/2018 00:00:00 and estimated end time of 08/10/2018 23:59:00
08/08/2018 12:49:46 AM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice
Estimated start Time of 08/08/2018 00:45:00 and estimated end time of 12/31/2999 23:59:00
08/07/2018 09:27:59 PM Implementation Tables for G.3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective until further notice.
Estimated start Time of 08/07/2018 20:42:00 and estimated end time of 08/14/2018 23:59:00
08/07/2018 11:36:38 AM DARU units for ARR 28C
Northport Steam Unit #1, 3 & 4 and Port Jeff Steam Unit #4 will be online for ARR 28C
Estimated start Time of 08/09/2018 00:00:00 and estimated end time of 08/09/2018 23:59:00
08/06/2018 02:41:58 PM DARU Port Jeff Steam Unit #3
Pt. Jeff Steam Unit #3 will be online for local reliability.
Estimated start Time of 08/08/2018 00:00:00 and estimated end time of 08/09/2018 23:59:00
08/06/2018 11:15:40 AM DARU units for ARR 28C
Northport Steam Units #1, 3 & 4 and Port Jeff Steam Unit #4 will be online for ARR 28C
Estimated start Time of 08/08/2018 00:00:00 and estimated end time of 08/08/2018 23:59:00
08/03/2018 11:36:30 AM DARU units for ARR 28C
Northport Steam Unit #1, 3 & 4 and Port Jeff Steam Unit #3 will be online for ARR 28C
Estimated start Time of 08/05/2018 00:00:00 and estimated end time of 08/07/2018 23:59:00
07/16/2018 01:43:16 PM DARU unit for ARR 28C
Port Jefferson Unit# 4 will be online for ARR 28C.
Estimated start Time of 07/18/2018 00:00:00 and estimated end time of 07/18/2018 23:59:00
07/16/2018 11:02:28 AM DARU units for ARR 28C
Northport Units # 2 and 4 will be online for ARR 28C
Estimated start Time of 07/18/2018 00:00:00 and estimated end time of 07/18/2018 23:59:00
07/13/2018 10:53:28 AM DARU units for ARR 28C
Port Jefferson# 4 and Northport# 2,3,4 will be online for ARR 28C.
Estimated start Time of 07/16/2018 00:00:00 and estimated end time of 07/17/2018 23:59:00
07/13/2018 10:51:45 AM DARU
Port Jefferson# 4 and Northport # 2,3,4 will be online for reliability beyond forecast.
Estimated start Time of 07/15/2018 00:00:00 and estimated end time of 07/15/2018 23:59:00
07/12/2018 01:18:51 PM Port Jefferson 4 DARU
Port Jefferson 4 DARU will be online due to gas leak on main gas supply.
Estimated start Time of 07/14/2018 00:00:00 and estimated end time of 07/14/2018 23:59:00
06/29/2018 11:34:16 AM DARU units for ARR 28C
Northport Steam Unit #1, 3 & 4 and Port Jeff Steam Unit #3 will be online for ARR 28C
Estimated start Time of 07/01/2018 00:00:00 and estimated end time of 07/01/2018 23:59:00
06/29/2018 11:28:15 AM DARU units for ARR 28C
Northport Steam Unit #1, 3 & 4 and Port Jeff Steam Unit #3 will be online for ARR 28C
Estimated start Time of 06/29/2018 00:00:00 and estimated end time of 06/29/2018 23:59:00
06/13/2018 10:31:25 AM DARU - Barrett Steam Unit #1 & #2
Barrett Steam Unit #1 and #2 will be online for local reliability
Estimated start Time of 06/15/2018 00:00:00 and estimated end time of 06/15/2018 23:59:00
06/11/2018 11:35:43 AM Test
Testing new link on the new website
Estimated start Time of 06/11/2018 12:00:00 and estimated end time of 06/11/2018 13:00:00
06/05/2018 03:21:55 PM Pt. Jeff GTs 2 and 3
Pt. Jeff GTs 2 and 3 will be dispatched for local reliability
Estimated start Time of 06/05/2018 14:30:00 and estimated end time of 06/05/2018 22:00:00
06/05/2018 01:19:39 PM Caithness
Caithness will be dispatched on duct burners for local reliability.
Estimated start Time of 06/05/2018 13:17:00 and estimated end time of 06/05/2018 22:00:00
05/07/2018 05:06:26 PM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice
Estimated start Time of 05/07/2018 17:00:00 and estimated end time of 12/31/2018 23:59:00
05/07/2018 05:05:31 PM TVR Guidance
TVR Guidance - "8KD West Bus (Holtsville) DRSS and 8DV Randall Rd (Wildwood) DRSS In Service" is in effect until further notice.
Estimated start Time of 05/07/2018 17:00:00 and estimated end time of 12/31/2018 23:59:00
04/30/2018 11:28:42 AM TVR Guidance
TVR Guidance - "8KD West Bus (Holtsville) DRSS In Service" is in effect until further notice.
Estimated start Time of 05/01/2018 00:01:00 and estimated end time of 05/04/2018 23:59:00
04/29/2018 05:29:09 PM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 04/29/2018 08:15:00 and estimated end time of 05/04/2018 23:59:00
04/13/2018 02:27:41 PM DARU of EF Barrett #2
EF Barrett #2 must be online to prevent an overload while transmission system work is conducted
Estimated start Time of 04/17/2018 00:00:00 and estimated end time of 04/20/2018 23:00:00
04/12/2018 02:22:57 PM DARU - Pt Jeff Steam Unit #3
Pt. Jeff Steam Unit #3 will be online for local reliability.
Estimated start Time of 04/14/2018 00:01:00 and estimated end time of 04/14/2018 23:59:00
04/12/2018 02:21:15 PM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice.
Estimated start Time of 03/19/2018 19:45:00 and estimated end time of 12/31/2018 23:59:00
03/14/2018 11:04:50 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective until further notice.
Estimated start Time of 03/13/2018 10:25:00 and estimated end time of 12/31/2018 23:59:00
02/01/2018 08:05:27 PM Implementation Tables for G.3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS In Service is effective immediately until further notice.
Estimated start Time of 02/01/2018 20:00:00 and estimated end time of 12/31/2018 23:59:00
01/30/2018 09:30:33 AM Implementation Tables for G.3
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately with tentative end date.
Estimated start Time of 01/29/2018 11:40:00 and estimated end time of 03/31/2018 23:59:00
01/09/2018 10:44:30 AM DARU - Barrett Steam Unit #1
Barrett Steam Unit #1 will be online for local reliability
Estimated start Time of 01/11/2018 00:00:00 and estimated end time of 01/11/2018 23:59:00
12/07/2017 01:25:24 PM
REVISED - Northport 3 will be online for PSEGLI transmission related work for 12/10@18:00 - 12/11@23:59
Estimated start Time of 12/10/2017 18:00:00 and estimated end time of 12/11/2017 23:59:00
12/07/2017 11:26:13 AM
Northport 4 will be online for PSEGLI transmission related work.
Estimated start Time of 12/10/2017 18:00:00 and estimated end time of 12/11/2017 23:59:00
12/07/2017 11:17:12 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 12/10/2017 23:59:00
12/04/2017 01:06:57 PM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 12/08/2017 23:59:00
12/02/2017 07:49:24 AM Test
This is a test
Estimated start Time of 12/02/2017 07:48:00 and estimated end time of 12/02/2017 08:00:00
11/29/2017 10:51:56 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 12/05/2017 23:59:00
11/27/2017 10:25:30 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 11/30/2017 23:59:00
11/20/2017 10:28:48 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 11/28/2017 23:59:00
11/16/2017 11:18:41 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 11/21/2017 23:59:00
11/15/2017 10:27:07 AM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/17/2017 00:00:00 and estimated end time of 11/17/2017 23:59:00
11/13/2017 01:22:59 PM Northport 4 DARU for Low Load
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/15/2017 00:00:00 and estimated end time of 11/16/2017 23:59:00
11/09/2017 02:42:02 PM Low Load Voltage Control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/11/2017 00:00:00 and estimated end time of 11/14/2017 23:59:00
11/06/2017 10:30:40 AM Northport 4 DARU for voltage control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/09/2017 00:00:00 and estimated end time of 11/10/2017 23:59:00
11/03/2017 09:58:58 AM Northport 4 DARU for voltage control
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/06/2017 00:00:00 and estimated end time of 11/08/2017 23:59:00
11/02/2017 12:56:01 PM Northport Steam Unit #4
Northport 4 will be online for NYSRC Reliability Rule - ARR 28A
Estimated start Time of 11/04/2017 00:00:00 and estimated end time of 11/05/2017 23:59:00
09/08/2017 11:13:11 AM PJ Steam Unit #4
Port Jeff Steam Unit #4 will be online for Local Reliability
Estimated start Time of 09/09/2017 00:01:00 and estimated end time of 09/10/2017 23:59:00
09/07/2017 04:47:58 PM PJ Steam Unit #4
Port Jeff Steam Unit #4 will be online for Local Reliability
Estimated start Time of 09/09/2017 00:01:00 and estimated end time of 09/09/2017 23:59:00
08/18/2017 07:49:19 AM East end generation
Forecast for weekend load on the south fork may require generating units to be dispatched for local security
Estimated start Time of 08/19/2017 06:00:00 and estimated end time of 08/20/2017 23:00:00
08/10/2017 08:14:19 AM East end generation
Forecast for weekend load on the South Fork may require generating units to be dispatched for local security
Estimated start Time of 08/12/2017 07:00:00  and estimated end time of 08/13/2017 23:00:00
08/04/2017 08:25:34 AM East end generation
Forecast for weekend load on the south fork may require generating units to be dispatched of local security
Estimated start Time of 08/05/2017 07:00:00 and estimated end time of 08/06/2017 23:00:00
08/01/2017 02:34:27 PM East End Generation Limitations
Do to transmission work on the LIPA system , Port Jeff, Shoreham, Wading River, Holtsville, Caithness, NYPA Flynn, Global, Southampton, East Hampton, Southold generation and CSC must not exceed 810 Mw with Long Island Control Area load at 2300 Mw and must be greater than 770 Mw at a LICA load of 3000 Mw.
Estimated start Time of 08/03/2017 23:00:00 and estimated end time of 08/04/2017 10:00:00
07/27/2017 07:26:25 AM East end generation
forecast for weekend load on the south fork may require generating units to be dispatched for local security
Estimated start Time of 07/29/2017 07:00:00 and estimated end time of 07/30/2017 23:59:00
07/21/2017 08:13:57 AM East end generation
Forecast for weekend load on the South Fork may require generating units to be dispatched for local security
Estimated start Time of 07/22/2017 06:00:00 and estimated end time of 07/23/2017 23:59:00
07/17/2017 10:50:40 AM DARU Units for ARR 28C
Northport #3 & #4, and Port Jeff Unit #4 will be online for ARR 28C.
Estimated start Time of 07/19/2017 00:00:00 and estimated end time of 07/21/2017 23:59:00
07/14/2017 08:14:42 AM east end generation
Forecasted load on the South fork may require generating units to be dispatched for local security
Estimated start Time of 07/15/2017 07:00:00 and estimated end time of 07/16/2017 23:59:00
07/07/2017 08:06:06 AM East end generation
forecast for weekend load on the south fork may require generating units to be dispatched for local security
Estimated start Time of 07/08/2017 07:00:00 and estimated end time of 07/09/2017 23:59:00
07/01/2017 06:46:04 AM South Fork Generation
Forecast for weekend load on the south fork may require generating units to be dispatched for local security.
Estimated start Time of 07/01/2017 07:00:00 and estimated end time of 07/02/2017 23:59:00
06/20/2017 11:29:42 AM DARU - PJ Steam Unit #4
Port Jeff Steam Unit #4 will be online for Loss of 138-881 & 138-882 on 138-871 with CSC OOS
Estimated start Time of 06/22/2017 00:00:00 and estimated end time of 06/22/2017 23:59:00
06/16/2017 02:17:15 PM 2HU GT 1 DARU
The reason for the DARU is the contingency loss of 69-260 on 69-261 with 69-270 out of service.
Estimated start Time of 06/18/2017 13:00:00 and estimated end time of 06/18/2017 20:00:00
06/02/2017 02:00:34 PM
Barrett Steam Unit #1 will be online for local reliability
Estimated start Time of 06/02/2017 06:00:00 and estimated end time of 06/08/2017 23:59:00
05/31/2017 10:36:17 AM
Barrett Steam Unit #1 will be online for local reliability
Estimated start Time of 06/02/2017 06:00:00 and estimated end time of 06/04/2017 23:59:00
05/27/2017 12:51:19 PM Implementation Tables for G-R3:
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS ? In Service is effective immediately.
Estimated start Time of 05/27/2017 12:48:00 and estimated end time of 12/31/2017 00:00:00
05/27/2017 03:50:14 AM Implementation Tables for G-R3:
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately.
Estimated start Time of 05/27/2017 03:04:00 and estimated end time of 05/30/2017 23:59:00
05/24/2017 01:31:32 PM
Barrett Steam Unit #2 will be online for local reliability
Estimated start Time of 05/20/2017 14:00:00 and estimated end time of 05/30/2017 23:59:00
05/22/2017 09:56:18 AM
Barrett Steam Unit #2 will be online for local reliability
Estimated start Time of 05/20/2017 14:00:00 and estimated end time of 05/26/2017 23:59:00
05/19/2017 01:30:08 PM
Far Rockaway GT #1 will be online for local reliability.
Estimated start Time of 05/22/2017 17:00:00 and estimated end time of 05/22/2017 22:59:00
05/18/2017 01:58:02 PM
Barrett Steam Unit #2 will be online for local reliability
Estimated start Time of 05/20/2017 14:00:00 and estimated end time of 05/23/2017 23:59:00
05/18/2017 01:57:17 PM
Barrett Steam Unit #1 will be online for local reliability.
Estimated start Time of 05/20/2017 00:00:00 and estimated end time of 05/20/2017 23:59:00
05/12/2017 11:46:54 AM Implementation Tables for G-R3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS - In Service is effective immediately.
Estimated start Time of 05/12/2017 11:43:00 and estimated end time of 12/31/2017 23:59:00
05/11/2017 10:53:47 AM
Barrett Steam Unit #1 will be online for local reliability
Estimated start Time of 05/08/2017 00:00:00 and estimated end time of 05/17/2017 23:59:00
05/09/2017 06:06:33 AM Implementation Tables for G-R3
Table 3 which assumes West Bus DRSS Out of Service and Wildwood DRSS In Service is effective immediately.
Estimated start Time of 05/09/2017 06:03:00 and estimated end time of 05/12/2017 15:00:00
05/05/2017 02:32:41 PM
Barrett Steam Unit #1 will be online for local reliability
Estimated start Time of 05/08/2017 00:00:00 and estimated end time of 05/13/2017 23:59:00
05/04/2017 06:38:23 PM Implementation Tables for G-R3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS - In Service is effective immediately.
Estimated start Time of 05/04/2017 18:26:00 and estimated end time of 12/31/2017 23:59:00
05/02/2017 07:43:16 PM Implementation Tables for G-R3:
Table 2 which assumes West Bus DRSS In Service and Wildwood DRSS Out of Service is effective immediately.
Estimated start Time of 05/02/2017 08:00:00 and estimated end time of 05/05/2017 15:00:00
04/28/2017 10:30:18 AM
Northport 1 will be online for reliability forecast beyond next day.
Estimated start Time of 04/30/2017 00:00:00 and estimated end time of 04/30/2017 23:59:00
03/25/2017 07:39:59 AM Additional generation will be online for local reliability
Due to current system conditions addition generation may be required between the hours listed above.
Estimated start Time of 03/25/2017 01:57:00 and estimated end time of 03/25/2017 22:00:00
03/25/2017 04:43:47 AM Additional generation will be online for local reliability
Due to current system conditions addition generation may be required between the hours listed above.
Estimated start Time of 03/25/2017 01:57:00 and estimated end time of 03/25/2017 09:00:00
03/17/2017 02:44:24 PM
PSEGLI Transmission Operations, PSEG ER&T, Versify and various generators met on Thursday March 16, 2017 at the PSEGLI Uniondale Office. The group reviewed and tested the new Generation Outage Management System.
Estimated start Time of 03/16/2017 09:00:00 and estimated end time of 03/16/2017 13:59:00
02/27/2017 02:40:57 PM
Far Rockaway GT#1 will be online for local reliability
Estimated start Time of 03/01/2017 08:00:00 and estimated end time of 03/01/2017 18:59:00
02/24/2017 10:24:48 AM
The total East End generation plus import (CSC, Port Jefferson, Flynn, Caithness, Shoreham, Islip RR, Stonybrook, Holtsville, Wading River, Southold, East Hampton) must be limited as follows LICA Load 1600 Mw: < 740 Mw, LICA Load 1750 Mw: < 790 Mw, LICA Load 1950 Mw: < 840 Mw, LICA Load 2050 Mw: < 875 Mw, LICA Load 2150 Mw: < 890 Mw, LICA Load 2350 Mw: < 945 Mw.
Estimated start Time of 02/28/2017 01:00:00 and estimated end time of 02/28/2017 18:00:00
02/24/2017 10:22:10 AM
The total East End generation plus import (CSC, Port Jefferson, Flynn, Caithness, Shoreham, Islip RR, Stonybrook, Holtsville, Wading River, Southold, East Hampton) must be limited as follows LICA Load 1600 Mw: < 740 Mw, LICA Load 1750 Mw: < 790 Mw, LICA Load 1950 Mw: < 840 Mw, LICA Load 2050 Mw: < 875 Mw, LICA Load 2150 Mw: < 890 Mw, LICA Load 2350 Mw: < 945 Mw.
Estimated start Time of 02/25/2017 01:00:00 and estimated end time of 02/25/2017 18:00:00
02/21/2017 03:26:05 PM
The combined output of Northport 3 and 4 is limited to approximately 500 MW.
Estimated start Time of 02/23/2017 00:01:00 and estimated end time of 02/23/2017 23:59:00
02/17/2017 02:10:02 PM
The combined output of Northport 3 and 4 is limited to approximately 500 MW.
Estimated start Time of 02/21/2017 00:01:00 and estimated end time of 02/21/2017 23:59:00
02/16/2017 11:33:37 AM
The output of Northport Steam Unit #1 will be limited to approximately 289MW.
Estimated start Time of 02/21/2017 00:01:00 and estimated end time of 02/22/2017 23:59:00
02/02/2017 10:13:16 AM
Glenwood GT 1 will be offline due to PSEGLI Transmission Related Work
Estimated start Time of 02/06/2017 05:00:00 and estimated end time of 02/15/2017 14:59:00
01/05/2017 04:28:51 PM Implementation Tables for G-R3
Table 4 which assumes BOTH West Bus DRSS and Wildwood DRSS ? In Service is effective immediately.
Estimated start Time of 01/05/2017 16:23:00 and estimated end time of 12/31/2017 00:00:00