PSEG Long Island is committed to strengthening the electric infrastructure and improving reliability and will be continuing to storm harden the system. Power On will focus on mainline circuits, the backbone of PSEG Long Island’s distribution system. The mainlines feed the many branch lines that power the homes and businesses in your community.

For a list of completed projects, visit the Town of Oyster Bay Completed Projects page.

 

Plainedge

The route will cover approximately 1.43 miles along an electric main line circuit. 
Start date: October 2020 
Posted date: October 1, 2020

PSEG Long Island crews will be working on the following streets: 
Hicksville Road between William Road and Ontario Avenue 
Jerusalem Avenue from just west of Hicksville Road to Flower Road


Villages of Bayville and Lattingtown

The route will cover approximately 1.3 miles along an electric main line circuit. 
Start date: September 2020 
Posted date: September 2, 2020

PSEG Long Island crews will be working on the following streets: 
Bayville Road between Waters Edge Court and Bayville Avenue 
Bayville Avenue between Bayville Road and east of School Street 
Godfrey Avenue between Peter Avenue and west of Robert Road 
Perry Avenue south of Peter Avenue and Godfrey Avenue


Villages of East Hills and Brookville

The route will cover approximately 3.11 miles along an electric main line circuit. 
Start date: July 2020 
Posted date: July 29, 2020

PSEG Long Island crews will be working on the following streets: 
Northern Boulevard between east of Addison Lane to west of Cedar Swamp Road 
Rear property east of Flamingo Road between Northern Boulevard and Tara Drive 
Rear property north of Tara Drive and south of Northern Woods Road between Flamingo Road and Peacock Drive 
Rear property east of Peacock Drive between Tara Drive and Falcon Road 
Rear property north of Falcon Road between Peacock Drive and Hummingbird Drive 
Rear Property east of Gold Coast Road between Northern Boulevard and Old Wheatley Road 
Private Road (off of Old Wheatley Road and east of Gold Coast Road) between Old Wheatley Road and Meadowbrook Lane


Massapequa, Village of Massapequa Park

The route will cover approximately 1 mile along an electric main line circuit 
Start date: June 2020 
Posted date: June 16, 2020

PSEG Long Island crews will be working on the following streets: 
Philadelphia Avenue between south of Pittsburgh Avenue and south of Illinois Avenue 
Philadelphia Avenue between Martin Place and Violet Street 
Violet Street between Philadelphia Avenue and Carmans Road 
Massachusetts Avenue between Atlantic Avenue and East Lake Avenue 
East Lake Avenue between Massachusetts and Euclid Avenue 
Carmens Road between north of Louden Avenue and Hemlock Street 
Hemlock Street between Carmans Road and Clocks Boulevard


Village of Matinecock and City of Glen Cove

The route will cover approximately 4.7 miles along an electric main line circuit 
Start date: June 2020 
Posted date: June 8, 2020

PSEG Long Island crews will be working on the following streets: 
Oyster Bay Road between Bayville Road and High Ridge Road 
Duck Pond Road between just west of Piping Rock Road to Oyster Bay Road 
Piping Rock Road between Underhill Road and Chicken Valley Road 
Long Island Rail Road right-of-way near Oyster Bay Road and Bayville Road


Wantagh and Seaford

The route will cover approximately 0.91 miles along an electric main line circuit 
Start date: May 2020 
Posted date: May 11, 2020

PSEG Long Island crews will be working on the following streets: 
Sunrise Highway (Route 27) between Seaford Avenue and Hicksville Road (Route 107) 
Railroad Avenue from just west of Sunrise Highway (Route 27) to Seaford Avenue 
Merrick Road between Fir Street and Seaford Avenue


Syosset and the Village of Oyster Bay Cove

The route will cover approximately 2.15 miles along an electric main line circuit 
Start Date: May 2020 
Posted Date: May 8, 2020

PSEG Long Island crews will be working on the following streets: 
Berry Hill Road between Northern Boulevard and Skyview Court 
Berry Hill Road between Foxhunt Cres and Hickman Street 
Northern Boulevard just west of Berry Hill Road 
Berry Hill Road between Baylis Place/Renee Road and Woodbury Way 
Woodbury Way between Berry Hill Road and Cold Spring Road 
Horton Place between Anita Avenue and Berry Hill Road 
Elliman Place between Split Rock Road and Anita Avenue 
Cold Spring Road between just west of Woodbury Way to Private Road (south of Iris Lane) 
Syosset-Woodbury Road between Cold Spring Road to Southwoods Road


Plainview

The route will cover approximately 2.8 miles along an electric main line circuit. 
Start Date: April 2020 
Posted Date: April 2, 2020

PSEG Long Island crews will be working on the following streets: 
South Oyster Bay Road between Woodbury Road to Meadow Lane 
New South Road between East Old Country Road to Meadow Lane 
Old Country Road between Gables Drive and South Oyster Bay Road 
Field Avenue between New South Road and South Oyster Bay Road 
Nassau Avenue between South Oyster Bay Road and just east of Orchard Street


Plainedge

The route will cover approximately 1.43 miles along an electric main line circuit. 
Start Date: April 2020 
Posted Date: April 2, 2020

PSEG Long Island crews will be working on the following streets: 
Hicksville Road between William Road and Ontario Avenue 
Jerusalem Avenue from just west of Hicksville Road to Flower Road


Plainview and Bethpage

The route will cover approximately 3.11 miles along an electric main line circuit.
Start Date: April 2020
Posted Date: April 2, 2020

PSEG Long Island crews will be working on the following streets:
Grohmans Lane between Old Country Road and Stewart Avenue
Haypath Road between Grohmans Lane and Plainview Road
Stewart Avenue between just west of Pine Avenue and Railroad Avenue
Hope Drive between Lillian Lane and Morton Drive and Peter Lane


Town of Oyster Bay

The route will cover approximately 3.49 miles along an electric main line circuit.
Start Date: Mid November 2020
Posted Date: November 5, 2020

PSEG Long Island crews will be working on the following streets:
Bayville Avenue between School Street and Centre Island Road
Ludlam Avenue between Bayville Avenue and W Harbor Drive
Centre Island Road between Bayville Avenue and just south of Beach Road
Walnut Place to Bayside Avenue
Bayside Avenue between Willow Place and the Long Island Railroad (LIRR)
North side of the LIRR Right of Way (ROW) running parallel to West End Avenue
North side of LIRR ROW behind Beekman Beach parking lot to W Shore Road